A growing software company needed a full floor ready before their lease on the old space ended. We planned the build-out backward from their move-in date and coordinated closely with building management.
01
The challenge
A fixed move-in date only 16 weeks after lease signing, in a fully occupied building.
02
Our solution
Long-lead items (glass, light fixtures, HVAC units) were ordered during permitting, and noisy work ran after 6 PM to protect other tenants.
03
The result
Certificate of occupancy in 14 weeks — the team moved in two weeks early.
02 — SCOPE
Scope
Demolition of previous tenant space
Glass-front meeting rooms
Open workstation layout
Living green wall
HVAC rebalancing
Data and AV infrastructure
03 — GALLERY
We moved in two weeks early. In commercial construction that basically never happens.